09/06/08 -  Concrete screed installed...

02/06/08 -  UFH pipe installed awaiting the concrete screed.

31/05/08 -  5” of insulation down in one of the smaller bedrooms to try out installing a DIY concrete screed over UFH.

15/11/07- The 1st floor UFH cupboard FINISHED!....

28/10/07- The 1st floor UFH cupboard....

28/10/07- The UFH manifolds with 2 port valves and balancing valves, pump & mixer valve and all 5 UFH circuit pipes attached and installed. Dry pressure tsted and ready for flushing...

26/10/07- The lower half and upper of the UFH manifold attached t mixer valve and pump...

26/10/07- The lower half (return) of the UFH manifold attached t mixer valve and pump... ....

25/10/07- The UFH pipe covered by 25mm rigid insulation...

22/10/07- The lower half (return) of the UFH manifold soldered up and ready for cleaning up ....

22/10/07- The 1st floor UFH pump/mixer/manifold design....

15/10/07- Cylinder fully plumbed and pipes lagged. Just some wiring fixing to do...

15/10/07- Cylinder fully plumbed...

02/10/07-New cylinder (with separate solar coil) in and solar circuit plumbed.

26/08/07- The UFH pipes underneath the first floor floor...

[Wychwood] [Progress Pictures] [Caravan Instalation] [Demolition] [Excavation] [The Build - Foundation] [The Build - Grnd Floor] [The Build - 1st Floor] [Guided Tour Videos] [The Oak Frame] [The 'Wings' Roofs] [The Main Roof] [Second Fix] [Caravan Out] [Cladding] [Fire Place & Chimney] [Drains] [New Garage] [UFH] [Landscaping] [Ground Floor] [Model Pictures] [Plans] [General Plot Pics] [The Old Caravan] [RSW's Photos] [EV Conversion] [Links]

29/08/08 -  Wall footings rebared and ready for concrete.  Looking North.  This will have a brick and concrete block retianing wall on it.  Further up it changes to brick and brick, non-retaining...